3 weeks to go
The opening of the new space is now 3 weeks away and the progress is in line with the plan. The major work is the painting of the ceiling, which is now approximately 50% complete. There is more painting being done by the parents; all the electrics are complete with the car park lighting added. Sealing has been started on the floor as has the refurbishment of the single bar, moved from the Offerton site. In the first progress post we were asking for blue floor tiles, some have arrived and they will be fitted once the dusty work is complete. Lots planned for next week so hopefully some less boring photos than the ones below.
We could still do with more parents helping with the painting. Let us know if you can help.