We attained planning permission during 2012 to change an industrial unit into a purpose built gymnastics facility.

Here is how we did it:

 

April 2012

Picked up the keys to our new home

 

 

April 2012

The Main Gym - Lots of work to do

 

May 2012

The bars move in

 

May 2012

Plenty of storage space

 

 

May 2012

First walls knocked down

 

June 2012

The painting starts

 

June 2012

The heating is in

 

 

June 2012

Starting the drainage for the female toilets

 

June 2012

There's the new store room

 

June 2012

Work starts in the dance studio

 

 

June 2012

More supplies arrive

 

June 2012

Say goodbye to the roller shutters

 

June 2012

More painting

 

 

June 2012

The female toilets are built

 

June 2012

Drainage starting to get sorted

 

June 2012

Still looking like a building site

 

 

June 2012

The reception area starts to take shape

 

July 2012

More supplies arrive

 

July 2012

The fancy new entrance

 

July 2012

Drains almost finished

 

 

July 2012

Starting to build the disabled toilets

 

July 2012

Its starting to look like a gym!!

 

July 2012

Painting starts in the new corridor

July 2012

Work starts on the bike shed

 

July 2012

The new corridor is coming along well

July 2012

The new beam mats have arrived

 

July 2012

Scaffolding goes up to finish the reception area

 

July 2012

Female toilets are getting put in

 

August 2012

The ceiling for the reception area is started

 

August 2012

The door frames have been installed

August 2012

The gate from Fred Perry Way is put in

August 2012

The floor is down in the toilets

 

August 2012

The ceiling of the reception area is begun

 

August 2012

Reception area is almost finished

 

September 2012

Things are getting the 'Stockport-Red' look

 

September 2012

Reception finished and the wall bars added

 

September 2012

The bike shed is finally in use

 

September 2012

The pre-school play equipment arrives

 

September 2012

The rest of the walls get painted

 

September 2012

The sign is up

 

September 2012

The store room is ready

 

September 2012

Disabled toilet and shower room nearly done

 

October 2012

The balcony looks much tidier now

 

October 2012

Our new floor has arrived

 

October 2012

First training on the new floor

 

October 2012

Female toilets are ready